Fire Station #2 will be located at the corner of Elk Lake Drive and Royal Oak Drive. The current building is well past its effective life and will be replaced with a new building. The entire site, recently consolidated from three District properties including a portion of Viewmont Ave., extends to the east near the highway and will also include the District’s fire training centre.
Updates and information
Residents, neighbours, and passers-by to the Fire Station No. 2 at 4595 Elk Lake Drive will have begun to see exciting changes to the site in the past five months. These changes reflect the beginning of a multi-year construction period and the fulfillment of the District’s capital investment priority to public safety in the Royal Oak Community with the construction of a new Fire Station.
Construction Update – August 2026
The construction project contractor, Knappett Projects Incorporated (KPI), mobilized on site from November 2023 to May 2024.
Over the past 25 months, since building construction began with excavation for the foundation, the following milestones have been reached:
- Building structure, envelope, mechanical and electrical systems, and interiors are 90% complete.
- Major site works of operations and training support facilities are 60% complete.
- Viewmont Avenue infrastructure and new cul de-sac are 70% complete.
Upcoming project milestones include:
- Offsite civil works installation:
- Viewmont Avenue new cul-de-sac concrete curbing and asphalt completion (by mid-September 2026).
- Royal Oak Drive and Elk Lake Drive are receiving new curbing and traffic controls, which reflect recently approved designs and specifications through Ministry of Transportation and Transit (MOTT) reviews.
- It is important to note that while Elk Lake Drive is a Saanich maintained street, the section of Royal Oak Drive in front of the fire hall is a provincially maintained street.
- This work, requiring several weeks of road work with on-site traffic management, is scheduled to be completed by the end of 2026.
- BC Transit services and bus stops will remain fully operational while road and curbside works are undertaken and new amalgamated bus stop locations are constructed on Royal Oak Drive eastbound, adjacent to their current locations.
- Saanich Fire Department apparatus equipment will not be deployed out of the new facility onto Royal Oak Drive until all off-site civil works are completed.
- Staff occupancy after building commissioning and occupancy permit approvals is planned for early Q4 2026.
- Finished landscaping on-site, including public pathway and Elk Lake Drive and Royal Oak Drive street side improvements are planned for Q4 2026 to Q1 2027.
- Contractor site de-mobilization, public art installation, and public opening event is planned for Q1 2027.
Project Information
The approved project budget is $44.6 million.
How will this improve Saanich?
Need more information?
Please contact fireadmin@saanich.ca.
