Current Projects

  1. Transportation Projects

  2. Sanitary Sewer Projects

  3. Storm Drain Projects

  4. Waterworks Projects  

Transportation Projects

Hampton Road Sidewalk and Way Finding Project

Start Date: Spring 2020
End Date: Summer 2020
Last Updated: October 2019
Budget: $550,000

Project Description:  The planned work on Hampton Road includes improvements to the sidewalk on the north side of the road, from Tillicum Road to Harriet Road.  Work will include installation of wheel chair accessible sidewalk drops, cycling way finding, and improvements to the Hampton Park parking lot.

Project Status:  In Design
Project Manager:
Stuart White

back to top

____________________________________________________________________________________

Royal Oak Avenue Sidewalk Upgrades

Start Date: Mid 2020
End Date: Late 2020
Last Updated: September 2019
Budget: TBD

Project Description:  The District of Saanich is undertaking an infrastructure project on Royal Oak Ave. The project includes upgrading the existing sidewalk on the north side of Royal Oak Ave. The project aims to complete the gap in sidewalk network and rebuild the asphalt pathway with standard concrete sidewalk.

Project Goals:  Royal Oak Ave, from Chatterton Way to Royal Oak Drive, will have universally accessible sidewalk on one side of the road right-of-way by 2020. The objective of this project is to design and construct universally accessible concrete sidewalk, separated wherever possible, on Royal Oak Ave.

Project Status:  Design
Project Manager: Claire Robinson

back to top

____________________________________________________________________________________

Blenkinsop Judge Pedestrian Crossing

Start Date: Late 2019
End Date: Early 2020
Last Updated: August  2019
Budget: $180,000

Project Description: The District of Saanich is undertaking an intersection upgrade project at Blenkinsop Road and Judge Place. The project includes the installation of a pedestrian controlled traffic signal at the intersection of Judge and Blenkinsop, sidewalk and accessibility improvements at the intersection, and bus stop improvements.

Project Goals: The intersection of Blenkinsop and Judge is a connection point between the trails at Playfair Park and the network of pathways east of Blenkinsop Road. Adding a pedestrian controlled traffic signal and other roadside mprovements will enhance the safety and accessibility at the intersection, and encourage alternative forms of transportation outlined in the Active Transportation Plan.

Project Status: Detailed Design
Project Manager: Graeme Galloway

back to top

____________________________________________________________________________________

Burnside Road Sidewalks - Helmcken Road to Little Road

Start Date: Summer 2019
End Date: Fall 2019 
Last Updated: August  2019
Budget: $85,000

Project Description: This project will include the installation of a new gravel sidewalks along Burnside Road between Helmcken Road and Little Road. Parking restriction signs will be installed to restrict vehicles parking on the gravel sidewalk area. A more formalized asphalt pull out will also be constructed at the mail boxes near Helmcken Road.

Construction is anticipated to begin in late August and last for approximately two weeks, pending favourable weather conditions. During the construction period crew and equipment will be on site between the hours of 9am and 3:30pm. Travel will be single lane alternating through the work zone. Please follow the direction of the crew and flagging personal.

Project Status: Construction Complete
Project Manager: Ashley Locke

back to top

____________________________________________________________________________________

Burnside/Helmcken Traffic Signal Upgrade

Start Date: May 2019
End Date: June 2019
Last Updated: September 2019
Budget: $400,000

Project Description:  This project will replace the aging traffic signals at the intersection of Burnside Road and Helmcken Road, and improve pedestrian facilities in the area. We are adjusting the intersection crosswalks to improve pedestrian safety, and adding or updating the corner ramps and traffic islands at the intersection to match the new crosswalk locations and provide improved shielding from vehicle traffic.

Project Status: Construction complete
Project Manager: Graeme Galloway

back to top

____________________________________________________________________________________

Caen Rd & Dieppe Rd Sidewalk – Dieppe Rd to Quadra St 

Start Date: Summer 2018
Finish Date: Summer 2019
Last Updated: April 2019
Budget: $400,000

Project Description:  This project is intended as a continuation of the newly constructed concrete sidewalk on Dieppe Rd to complete the gap in pedestrian facilities between Dieppe Road and Quadra Street. Construction for this project will be done in two phases. Phase one includes new sidewalk on the corner on Quadra Street and Caen Road in preparation for asphalt overlay along Quadra Street. Phase two includes the continuation of the new sidewalk along Caen Road towards Dieppe Road and along Dieppe Road to the north back towards Quadra Street. For more information, please review the Caen & Dieppe Conceptual Plan [PDF - 3 MB].

Project Status: In Construction
Project Manager: Ashley Locke

back to top

____________________________________________________________________________________

Feltham Road Re-laning – Shelbourne St to Tyndall Ave

Start Date: Fall 2018
Finish Date: Spring 2019
Last Updated: July 2019
Budget: $600,000

Project Description:  This project is driven by the Active Transportation Plan and will provide improvements to sidewalks and new dedicated cycling facilities along Feltham Rd from Shelbourne St to Tyndall Ave. Plans include road re-laning, buffered bike lanes, a full pavement overlay and improvements to existing sidewalks.

Construction will be completed in two phases. Phase one includes repairs to the road base, repairs to the storm drain system and replacement of sub-standard sidewalk to be constructed in the fall and winter of 2018. Phase two includes a new asphalt road surface and new road lane markings to be constructed in the spring of 2019.

Project Display Board [PDF - 1 MB]

Project Status: Complete
Project Manager: Ashley Locke

back to top

 ____________________________________________________________________________________

Finnerty Road - McKenzie Ave to Arbutus Rd Infrastructure Upgrade Project

Start Date: Early 2019
End Date: Summer 2019
Last Updated: July 2019

Project Description:  This project will infill new concrete sidewalks, install dedicated protected bike lanes and place an asphalt overlay between the roundabout at McKenzie Ave and Arbutus Rd. Currently, there are gaps in the curb and sidewalks and no bike lanes on Finnerty Rd. The project will also replace and upgrade 510 meter of aging water mains to improve fire flows and upgrade to LED streetlights.

Project Goals:

  • Provide safe facilities that promote safe streets and more people walking and riding bikes
  • Close sidewalk and cycling gaps
  • Rehabilitation of aging underground infrastructure
  • Provide access to the nearby middle school and UVic
  • Improve available fire flows
  • Reduce frequency of unplanned service interruptions
  • Save energy and reduce CO2 emissions

Finnerty Display Board

Project Status: In Construction
Project Manager: Ben Lubberts

back to top

____________________________________________________________________________________

Ridgebank Cres Reconstruction – Carey Rd to Vanalman Ave

Start Date: Winter 2019
Finish Date: Summer 2019
Last Updated: April 2019
Budget: $830,000

Project Description: This project will include the reconstruction of the road base and asphalt paving to improve road conditions along Ridgebank Crescent between Carey Road and Vanalman Avenue. Upgrades to the sidewalk corner ramps near the intersections of Carey Rd, Springridge Cres, and Vanalman Ave will also be included. Upgrades to the storm and sewer mains will be completed prior to road reconstruction.

You may wish to review the conceptual plan [PDF - 2 MB] of the improvements.

Project Status: Construction Complete
Project Manager: Ashley Locke

back to top

____________________________________________________________________________________

Shelbourne Street Improvements Project (SSIP)

We've created a dedicated web page for this comprehensive project - please click here.

back to top
 _____________________________________________________________________________________

West Saanich Road and Prospect Lake/Sparton Road Intersection - Conceptual Design

Start Date: April 2019
Last Updated: October 2019

Project Description: Saanich is working with a design consultant to complete the conceptual design of a full intersection upgrade at West Saanich Road and Prospect Lake/Sparton Road. This will include improvements to traffic flow with safe access in all directions by pedestrians, cyclists and motorists to the Prospect Lake Elementary School, nearby businesses and the Interurban trail.

Project Goals:

  • Improve traffic movements at the intersection
  • Provide safe facilities that promote safe streets and more people walking and riding bikes
  • Extend pedestrian pathway/walkway from Whitehead Park at Goward Road to the Community Hall to close any gaps
  • Upgrade Watermain Design from the intersection to the Prospect Lake school

Update as at October 15, 2019: 

The project’s design consultant has presented The District with two recommended options for improvement of West Saanich – Prospect Lake/Sparton intersection and a sidewalk from Whitehead Park at Goward Road to Prospect Lake Community Hall.

The proposed concepts were developed with consideration taken to the existing and 20 year projected traffic volumes, surrounding topography, proximity of local school and businesses locations and accessibility to therein, geotechnical findings, environmental impacts, soil quality assessment, and a tree survey.

Based on these findings, the project design consultant’s recommended two preferable options for the intersection – a roundabout and a signalized intersection. Included in their submission is a sidewalk design which begins at Goward Road and connects to the Community Hall on Sparton Road.

Thank you to all who attended our open house. For those who could not make it, please fill out a comment sheet and email it to engineering@saanich.ca by November 24, 2019.

Concepts and the technical memorandum

 

Project Status: Conceptual Design
Project Manager: Vira Pikhteryeva

back to top

_____________________________________________________________________________________

West Saanich Road - Quadra St to Royal Oak Shopping Centre

Start Date: Summer 2019
End Date: Winter 2020
Last Updated: May 2018

Project Description:  This project is a final phase of West Saanich Rd Street Scape, which fulfills key policies identified in the District’s Official Community Plan, completes gaps in the cycling and pedestrian facilities along West Saanich Road, and provides safe alternate modes of transportation.

Along with the installation of buffered bike lanes, concrete sidewalks, LED street lighting, upgrade of bus stops, installation of a new mid-block crosswalk connecting two bus stops, planting of significant amount of new trees, an asphalt overlay will take place from Quadra St to Royal Oak Shopping Centre.

All of the above will be a significant improvement to West Saanich Rd providing welcoming facilities for everyone to enjoy. 

For proposed design drawing, please see West Saanich Display Board.

Project Status: In Construction
Project Manager: Vira Pikhteryeva

back to top

_____________________________________________________________________________________

Wilkinson Rd - Greenlea Ave to Travino Lane Rd Improvements

Start Date: Early 2019
End Date: Summer 2019
Last Updated: August 2019
Budget: $1,125,000
 
Project Description:  The planned improvements for this project are to provide pedestrian and cycling facilities that contribute to a more balanced mode share along Wilkinson Rd from Travino Lane to Greenlea Dr. This project will include the installation of concrete sidewalks on the east side of the road, painted bike lanes, improved bus stops, and intersection improvements at Greenlea Rd.
 
Project Status: Construction Complete
Project Manager: Stuart White 
back to top

____________________________________________________________________________________

Sanitary Sewer Projects

Orillia Storm & Sanitary Pipe Replacement

Start Date: Late October 2019
End Date: Estimate 3 months duration
Last Updated: October 2019

Project Description: The District of Saanich will be replaceing 252 meters of storm drain and 262 meters of sanitary sewer pipes along Orillia and Obed.  This is being done to upgrade aging pipes as part of our on-going infrastructure improvement program.  Although we will try to accommodate local residents, you should expect some delays during construction. On-street parking will also be limiited.

Orillia Storm & Sanitary Project Notification Sept 2019.pdf [PDF - 305 KB]

Project Status: Construction Scheduled
Project Manager: Peter Kelley

back to top

______________________________________________________________________

Parkside Crescent/Jamaica Road/Winchester Road, and Cedar Hill Road - Replacement of underground infrastructure

Start Date: May 2019
End Date: November 2019
Last Updated: November 2019
Budget: $2,784,474

Project Description: Contractors will be undertaking a project to replace the water, sanitary sewer, and drain mainlines/services in this area. There will be some street parking and driveway access issues due to the nature of the work. Contractors will have steel plates on site to span a trench if access is urgent during the day. The trenches will be backfilled on a daily basis. Contractors will be cordoning off the next day's stretch with yellow caution tape, and respectfully ask that residents and visitors not park in these areas. 
There will be some minor interruptions with respect to the water service tie-ins. Residents of affected households will be notified at least 24 hours in advance of these interruptions by way of written notice. These interruptions will likely be 4-8 hours in duration. The District of Saanich will be completing all connections to existing mains.

Project Status: In construction
Project Manager:
Jeff Butcher

back to top

______________________________________________________________________

Storm Drain Projects

Haliburton Road Phase 4 - Pat Bay Hwy to Wesley Road

Start Date: August 2019
End Date: October 2019
Last Updated: July 2019
Budget: $450,000

Project Description: Saanich is going to be upgrading the storm drain network along Haliburton from the Pat Bay HWY to Wesley Road. This project is the 4th phase of a 4 phase Roadway and Drainage improvement project which fulfills key policies identified in the District’s Official Community Plan. During construction, vehicle access will at times be restricted to a single lane.

Project Status: Construction Scheduled
Project Manager: Graeme Galloway

back to top

______________________________________________________________________

Bowker Creek Bank Rehabilitation Project

Start Date: August 2019
End Date: mid-September2019
Last Updated: July 2019
Budget: $300,000

Project Description: Saanich will be undertaking repairs on the south bank of Bowker Creek where erosion has occurred. Please review the Bowker Creek Bank Rehabilitation Project Notification [PDF - 429 KB] for more information.

Project Status: Construction Scheduled
Project Manager: Peter Kelly

back to top

______________________________________________________________________

Ridgebank Crescent reconstruction - Vanalman Avenue to Carey Road

Start Date: April 2019
End Date: July 2019
Last Updated: May 2019
Budget: $400,000

Project Description: Replacement of portions of the storm and sewer mains are underway along the Ridgebank Rd right of way from Carey Rd. to Vanalman Ave. This project is being completed in conjunction with the above transportation project that involves the reconstruction of the road base and asphalt paving to improve road conditions along Ridgebank Crescent between Carey Road and Vanalman Avenue. 

Project Status: In construction
Project Manager: Jeff Butcher

back to top

______________________________________________________________________

Waterworks Projects

Spring Bay Road, Medway Street & White Rock Street

Start Date: Late 2020
End Date: Early 2021
Last Updated: November 2019

Project Description: The District of Saanich is replacing 362 meters of water main on Spring Bay Road, Medway Street and White Rock Street.  This upgrade is required due to the age and condition of the main and will also increase the water capacity and water quality for the area.  During construction, vehicle access will at times be restricted between 8:00 am and 4:00 pm from Monday to Friday.  Traffic control personnel and signage will be in place to help direct vehicles, cyclists and pedestrians through or around the work site as required.

 Spring Bay Road, Medway Street & White Rock Street Notification.pdf [PDF - 499 KB]

Project Status: Planning
Project Manager: Adam Overend

back to top

______________________________________________________________________

Veteran, Freeman & St Matthews

Start Date: Early November 2019
End Date: April 2020
Last Updated: October 2019

Project Description: Saanich will be replacing the watermain on Veteran, Freeman and St Matthews, and sanitary sewer and storm drain on Veteran and Freeman.  The purpose of this project is to upgrade aging pipes as part of our ongong infrastructure improvement program.  Although we will try to accommodate local residents you should expect some traffic delays during construction.  On street parking will also be limited.  Construction areas include Veteran from Knight to Cedar, Freeman from Veteran to Shelbourne and St Matthews from Freeman to Derby.

Veteran SDW Project Notification.pdf [PDF - 407 KB]

Project Status: Construction Scheduled
Project Manager: Peter Kelly

back to top

______________________________________________________________________

Foul Bay Road Watermain Upgrade

Start Date: September 2019
End Date: June 2020

Last Updated: September 2019

Project Description: The District of Saanich will be replacing 1,150m of watermain along Foul Bay Road from Haultain Street to Lansdowne Road. This project is for replacement of old, undersized watermain and will improve fire flows to the area.

Construction will be done in two phases. Phase 1, from Allenby Street to Lansdowne Road, will be starting in September and be complete by January. Phase 2, from Allenby Street to Haultain Street, will start approximately 1.5 months after completion of Phase 1. Our estimate is that Phase 2 will start in February and be complete by June.
 
During construction, two lanes of traffic will be maintained on Foul Bay Rd, however delays should be expected periodically. During work hours, cyclists will share the travel lanes with vehicles.
 

Project Status: Under Construction
Project Manager: Nathan Robertson

back to top

 ______________________________________________________________________

Blenkinsop Road Watermain Upgrade

Start Date: October 2019
End Date: November 2019
Last Updated: October 2019

Project Description: Saanich will be replacing 110m of watermain along Blenkinsop Road, from the Root Cellar driveway through to the other side of the McKenzie Avenue intersection.  The purpose of this project is to replace an aging section of watermain in advance of future paving on Blenkinso Road.  During construction, two lanes of traffic will be maintained along Blenkinsop.  Expect traffic delays during construction.

Blenkinsop Road:  McKenzie Ave to Root Cellar Driveway [PDF - 458 KB]

Project Status: Construction Scheduled for week of October 7, 2019
Project Manager: Nathan Robertson

back to top

______________________________________________________________________

Sims Avenue Multi-Utility Upgrade

Start Date: Early 2020
End Date: Expected to take four months to complete
Last Updated: September 2019

Project Description: Saanich will be undertaking a utility upgrade project on Sims Ave from Wascana St to the dead-end of Sims at Battleford Ave. Scope of the underground work includes replacement of water, sanitary and storm mains and services. Surface work will include full-width asphalt overlay from Seaton St to Wascana St and trench patching from Wascana St to the dead-end. Construction will be performed by a Contractor not yet named.

Project Status: Construction Scheduled
Project Manager: Nathan Robertson

back to top

______________________________________________________________________

Regina Avenue Multi-Utility Upgrade

Start Date: Early 2020
End Date: Expected to take four months to complete
Last Updated: September 2019

Project Description: Saanich will be replacing all water, sanitary and storm mains and services on Regina Ave from Tillicum Rd to Wascana St. We will also be doing full-width asphalt overlay. This construction project will be performed by a Contractor not yet selected.

Project Status: Construction Scheduled
Project Manager: Nathan Robertson

back to top

______________________________________________________________________