Phase 1 Construction Updates

June 2022

  • Line painting completed
  • Majority of the project is now complete
  • The Contractor will be on-site occasionally over the next few months repairing minor deficiencies

May 2022

  • Street furniture installed
  • All sidewalk and median construction complete
  • New trees and plantings installed

April 2022

  • Final paving completed on April 2nd
  • Remaining work includes line painting, landscaping, street furniture installation and minor sidewalk construction
  • Majority of construction is scheduled to be complete by the end of May

March 2022

  • Majority of sidewalk construction completed
  • Road base prepared for final paving

December 2021

  • All new curbs built between Home Depot driveway and Garnet Road
  • Paving from Home Depot driveway to Garnet Road was not completed this year due to weather conditions. Completion of paving works has been posponed until March 2022 (weather permitting)
  • Some work will be taking place over January and February but there will be periods where the contractor is not on site.  Much of the remaining work cannot be done until paving is completed.
  • Construction is scheduled to be complete by April 2022 (weather permitting)

November 2021

  • Curbs and sidewalks completed between the Home Depot driveway and Torquay
  • Nov. 21 - Paving completed between the Home Depot driveway and Torquay

October 2021

  • New traffic signal upgrades completed at McKenzie, Home Depot driveway, Blair and Feltham

August 2021

  • Water system upgrades completed

May 2021

  • Intersection and roadwork under construction

April 2021

  • Night work at McKenzie intersection starting April 12, expected to last for two weeks

February 2021

  • Sanitary sewer and storm drainage upgrades complete

January 2021

  • Water system upgrades started

July 2020

  • Installation of new traffic signals at Torquay/Shelbourne and Feltham/Cedar Hill completed

May 2020

  • Sanitary sewer and storm drainage upgrades started

April 2020

  • Chew Excavating began construction.
  • The contractor is required to include safe work methods in their safety plan for effective mitigation of COVID-19 exposure and the safe performance of their work.
  • Work starts on the new traffic signals at Torquay/Shelbourne and Feltham/Cedar Hill