What's been done

April 2020

Phase 1 

  • Chew Excavating (a Division of Ralmax Contracting Ltd.) began construction.
  • Contractor required to include safe work methods in their safety plan for effective mitigation of COVID-19 exposure and the safe performance of their work.

Phase 2

  • Planning for design underway.

March 2020

Phase 1 

  • Saanich Municipal Council approved awarding of the Tender to Ralmax contracting Ltd.
  • Planning for construction underway.

December 2019

Phase 1 

  • Design completed;
  • Public Tender for construction issued.