Completed Projects

Broadway Watermain Replacement

Start Date: August 2017
End Date: October 2017
Budget: $432,000

Project Description: The District of Saanich replaced 490 meters of water main on Broadway Street, from Raymond Street North to Glanford Avenue and continuing on the other side of Glanford until the strata property at 640 Broadway Street. This upgrade was necessary because of the age and condition of the main and will increase the water capacity and fire flow to the area.

Project Status: Complete
Project Manager: Nathan Robertson

____________________________________________________________________________________

Linwood Avenue Sidewalk                    

Start Date: March 2017
End Date: July 2017
Budget: $500,000

Project Description: Improve pedestrian accessibility towards Cloverdale Traditional School and the Four Corners Village area.

Project Status: Construction Complete.
Project Manager:  Brad Ormiston

Linwood Sidewalk Concept Plan [PDF - 1 MB]____________________________________________________________________________________

West Saanich Road Sidewalk - Elk to Pipeline

Start Date: August 21, 2017
End Date: Fall 2017
Budget: $750,000
 
Project Description: The District of Saanich has identified walkability, and safer routes for all modes of transportation the highest priority as part of our strategic plan. Between 1998-2000 the West Saanich Streetscapes plan was created by municipal and residential stakeholders as a collaborative document to create a vision for West Saanich Road. The plan was endorsed by Council in 2001. The District will be undertaking a sidewalk and bike lane project on West Saanich between Elk and Pipeline in the upcoming months.This project will include construction of a concrete sidewalk, painted bikelanes along West Saanich connecting the gap between Elk Lake and Pipeline road, and planted median.
 
Project Status: Complete
Please check out the preliminary display drawing [PDF - 575 KB]showing the extent of the project.

Project Manager: Sandra Liddell

____________________________________________________________________________________

Wilkinson Bridge/Colquitz River Trail

Start Date: Spring 2016
End Date: July 2017
Budget: $6,500,000

Project Description: The Wilkinson Bridge Replacement / Colquitz Trail Extension project replaces a critical piece of transportation infrastructure while providing new bike lanes, sidewalks, trails and upgrades to utility infrastructure.

Project Status:  Project Complete
Project Manager:  Sandra Liddell